铸铁护栏及预埋件安装工艺是怎样的?

来源:http://www.kpp647.com添加时间:2020-08-18 11:32:09

  下面为大家介绍一下铸铁护栏及预埋件安装工艺:

  The following is to introduce the installation process of cast iron guardrail and embedded parts:

  铸铁护栏水平安装工艺:铸铁护栏均按照所提供的标准线来进行水平安装。

  Cast iron guardrail horizontal installation process: cast iron guardrail is installed horizontally according to the standard line provided.

  铸铁护栏安装流程:

  Installation process of cast iron guardrail:

  1.产品到达施工现场后按图纸上所规定的位置及尺寸准确安装就位,确定好标高及垂直平整度。应按照甲方要求与图纸设计要求进行定位,确保达到设计要求与验收规范。

  1。 After arriving at the construction site, the products shall be installed in place according to the position and size specified in the drawings, and the elevation and vertical flatness shall be determined。 Positioning shall be carried out according to Party A's requirements and drawing design requirements to ensure that the design requirements and acceptance specifications are met。

  2.预埋件安装根据图纸设计要求和施工现场的实际情况准确无误的定位,避免造成不在一条平行线上。

  2. The installation of embedded parts shall be accurately positioned according to the design requirements of drawings and the actual situation of the construction site, so as to avoid not being on a parallel line.

              山东铸铁护栏

  3.铸铁护栏安装按所提供的标准线抄水平定位安装,预埋间距根据现场尺寸及图纸设计要求,安装定位。

  3. The cast iron guardrail shall be installed horizontally according to the provided standard line, and the embedded spacing shall be installed and positioned according to the site size and drawing design requirements.

  4.安装偏差必须符合国家规定和设计要求,达到验收标准。

  4. The installation deviation must meet the national regulations and design requirements, and meet the acceptance standards.

  5.预埋件、铸铁护栏安装必须牢固,安装偏差根据国家规定和设计要求:直线度<3mm,垂直度<3mm,栏杆间距误差<3mm,对角线误差<3mm,预埋件垂直误差<3mm,水平误差<3mm。

  5. The embedded parts and cast iron guardrail must be installed firmly, and the installation deviation shall be in accordance with the national regulations and design requirements: straightness < 3mm, verticality < 3mm, spacing error of railings < 3mm, diagonal error < 3mm, vertical error of embedded parts < 3mm, horizontal error < 3mm.

  6.预埋件安装定位准确无误经验收后刷两道防锈漆,再进行铁艺栏杆安装。

  6. The installation and positioning of embedded parts shall be accurate. After acceptance, two layers of antirust paint shall be applied, and then the iron railing shall be installed.

  以上介绍的是铸铁护栏及预埋件安装工艺,希望大家有所了解。

  The above is the cast iron guardrail and embedded parts installation process, I hope you have some understanding.



  • 济南顺健金属制品秒速赛车玩法 地址:山东省济南市天桥区金牛建材市场  
  • 电话:  手机号:18706412842 本网站由提供技术支持  流量统计:
二维码
济南万顺铸业秒速赛车玩法主要为大家提供山东球墨铸铁井盖铸铁护栏落水斗给水管排水管暖气片等产品的批量制作和安装服务,欢迎大家前来选购!
秒速赛车玩法 128彩票 秒速时时彩 快3平台 秒速赛车计划 秒速赛车注册 江苏11选5 秒速赛车计划 pk10开户